On this page
Project Overview
The National Capital Authority is undertaking a major project at Scrivener Dam. The project will involve strengthening work on the downstream structure of the dam – the dissipator. These works are the most significant strengthening works completed on the dam since it was first built in 1963.
About Scrivener Dam
Scrivener Dam is a concrete gravity dam responsible for retaining the water which forms Lake Burley Griffin. It plays a critical role in controlling the flow of water and managing the risk of floods by controlling water levels in Lake Burley Griffin at a consistent level through five flood gates and three sluice gates, which in turn protects the residents of Canberra from flooding and downstream areas from sudden fluctuations in water flows.
Learn more about the dam on the Scrivener Dam Attractions page.
About the project
The spillway, located immediately downstream of the dam, includes a dissipator structure. The dissipator is a concrete structure comprising of a horizontal concrete slab and concrete chute blocks and vertical concrete baffle blocks. The dissipator absorbs the energy of the water flowing over the flood gates and prevents potentially damaging erosion in the river channel downstream of the dam. The chute and baffle blocks disperse water and reduce the impact of water pouring over the horizontal concrete slab structure.

Since the dam was first constructed in 1963, standards of construction and the body of knowledge regarding dam safety have improved. Based on several investigations and studies undertaken in recent years, the NCA identified several structural risks with the dissipator of the dam.
During flood conditions, there is a risk the dissipator structure could fail, which in turn could cause the dam to fail. Hence, the dissipator strengthening project is essential to ensure the ongoing safety of the dam.
Project benefits
- Mitigate the risk of failure of the dissipator structure and, in turn, ensure ongoing safety of Scrivener Dam.
- Mitigate risk of flooding to surrounding community during flood events.
- Ensure contemporary standards are met.
- Improve safety.
Project key features
- Strengthening the existing horizontal concrete slab of the dissipater by installing approximately 700 new ground anchors into the foundation rock of the dam (10 to 20 metres deep).
- Increasing the thickness of the horizontal concrete slab of the dissipator by half a metre.
- Reconstructing new baffle blocks to match the increased thickness of the concrete slab.
- Reinforcing the adjacent riverbanks downstream of the dam to minimise erosion that could lead to failure of the dissipater structure.

Construction
Seymour Whyte was awarded the construction contract in December 2024.
Site works began in April 2025 with major works underway from June 2025 and expected to be completed in October 2027.
During construction there will be an increase in construction traffic on Lady Denman Drive. Construction traffic will enter the site on the western access road to Scrivener Dam and will cross the existing bike path adjacent to Lady Denman Drive. Traffic will be controlled during construction hours however we urge all users to take care when navigating the area.
Lowering of Lake Burley Griffin
To manage risks associated with working in the spillway of the dam, it is necessary to lower the level of the lake during construction. It is planned to lower the lake by a maximum of 500mm during construction. This will be reduced as far as possible to minimise the impact to lake users. We urge all lake users to consider the impacts and potential new hazards prior to setting out onto the water.
Construction staging
Major works are being carried out in two main stages as shown in the image below. The stages will be separated by a temporary cofferdam which will allow operation of the dam around the construction site.
What is a cofferdam?
A temporary enclosure built within or around a body of water to create a dry area for construction or repair work.
Both stages consist of demolition of the existing baffle blocks, installation of ground anchors into the foundation rock, pouring of the new reinforced concrete slab and reconstruction of the baffle blocks on top of the new slab.
Stay up to date
Receive regular updates direct to your inbox; simply sign up using the form below
Click on the following links to view our Privacy Policy and Terms of use.
If you would like to contact the project team, email us at communications@nca.gov.au
Publications and previous announcements
2 December 2024: Project to Strengthen Scrivener Dam Moves Ahead
16 November 2023: Public Notification - Scrivener Dam Strengthening Project Call for EOIs
31 March 2022: Scrivener Dam to get needed upgrade