4 April 2025
The NCA is lowering the water level of Lake Burley Griffin to support construction works for the Scrivener Dam Dissipator Strengthening Project.
The water level will be lowered by up to 250 millimetres with an additional drawdown of up to 250mm scheduled to take place in May, if required.
The water level will remain up to 500mm below normal levels until construction works for the Scrivener Dam Dissipator Strengthening Project are completed.
The NCA is undertaking a major strengthening project at Scrivener Dam. The project will involve strengthening work on the downstream structure of the dam – the Dissipator.
Scrivener Dam is a concrete gravity dam. The design and mass of the dam retains the water which forms Lake Burley Griffin. The Dam is equipped with five flood gates and three sluice gates, all of which are used to control the water level in Lake Burley Griffin.
The spillway located immediately downstream of the dam includes a dissipator structure. The dissipator is a concrete structure comprising of a horizontal concrete slab, concrete chute blocks and vertical concrete baffle blocks. The dissipator absorbs the energy of the water flowing over the flood gates and prevents potentially damaging erosion in the river channel downstream of the dam.
The dam plays a critical role in controlling the flow of water and managing the risk of floods by controlling water levels at a consistent level, that in turn protects the residents of Canberra from flooding and downstream areas from sudden fluctuations in water flows. These work s will be the most significant strengthening works completed on the dam since it was first built in 1963.
Studies commissioned by the NCA identified the need to strengthen the Scrivener Dam Dissipator. NCA worked with the University of New South Wales Water Research Laboratory (UNSW WRL), and the Dam Safety Engineers (SMEC) to design, construct and test a scale model of Scrivener Dam. The model and other investigative methods were used to ascertain how the dam and its environs function under a range of operational scenarios.
The modelling and subsequent assessments identified structural risk with the dissipator under flood conditions. There is the potential for the dissipator to be significantly damaged during a major flood event, which in turn, could lead to the failure and subsequent collapse of Scrivener Dam. The project will involve:
The strengthening work will ensure the ongoing safety of the dam during flood events.
Learn more about the Dam on the Scrivener Dam Attractions page.
Construction Works
The $36 million project has been awarded to Seymour Whyte, following an open tender process by the National Capital Authority (NCA).
Early works for the project are expected to commence by December 2024.
Construction works on site are expected to commence in March 2025 and will be completed by mid-2027.
The level of Lake Burley Griffin will be lowered by up to 500mm for the duration of construction works on site.
NCA is working with key external stakeholders to mitigate impact to use of the lake.
Public Interest Certificate
A Public Interest Certificate has been issued. Click here to view the Public Interest Certificate.
We are keen to keep the community involved and aware as to what’s happening at Scrivener Dam. Keep checking back on this website and register for project updates.
We acknowledge the Ngunnawal people as traditional custodians of the ACT and recognise any other people or families with connection to the lands of the ACT and region.
We acknowledge and respect their continuing culture and the contribution they make to the life of this city and this region.