Boundless parking extension

Location
Kings Park, Parkes
Project Type
Construction
Landscaping
Construction Start Date
October 2020
Completion Date
December 2020
Temporary Road or Lake Closures
No

_________________________________

Update 17 December 2020

The Boundless parking extension works have been finalised with 44 new spaces now available to use. Minor landscaping will continue into the new year to finish off the whole project. 

_________________________________

On behalf of the National Capital Authority (NCA), Woden Contractors have commenced works to extend the Boundless car park.

With limited parking in the area and the growing popularity of the playground the car park extension will see the addition of 44 new spaces. Four of these will be new accessible car spaces.

The project will see some trees removed to accommodate the new parking facility, however 56 trees will be re-instated to the site ensuring a sustained tree canopy in the area.

Works are scheduled to be completed by January 2021.

Parking at this car park is mostly unaffected with only one of the current parking bays utilised by the site compound.

Boundless Parking extension_November 2020

Boundless Parking extension_November 2020

Parking extension construction at Boundless Playground

Landscape Drawing_Boundless parking extension