Old Parliament House Precinct - Path and Carpark Upgrades

Project Update

Throughout December and January the project has progressed with new kerbs, kerb ramps, exposed concrete paths and asphalt carpark surfaces being constructed within the Northern carparks. 

The front western car park was completed in late December - ahead of schedule. 

The front eastern car park is currently underway with expected completion by early February 2026 to avoid any clash with the upcoming Enlighten Festival.