Latest Update
June 2025
Site investigations and lead in works, including locating services, are programmed to commence from 24 June 2025.
This work will be undertaken during normal business hours.
Construction works are then scheduled to commence onsite from 7 July 2025.
Works will be delivered weekdays and weekends, with no nights works currently planned.
A full closure at the intersection of Cresswell Street and Constitution Avenue with be implemented across multiple weekends, with detours in place for traffic.
The following weekends have identified for the intersection closures to be implemented:
The weekday and weekend closures will not impact any access to surrounding buildings or businesses.
The weekend closures will however impact bus services to the area. The NCA has been working with ACTION buses to confirm bus stop closure and bus detour requirements.
The following information regarding the impacts will be posted on affected bus stops:
Advertisement and communication of all lane and road closures during the works will be posted in the next update.
Project Summary
This infrastructure upgrade is the continuation of the existing median along Constitution Avenue and will include landscaping.
The works are due to commence in July 2025 and be complete by September 2025.
During the project there will be some periods of weekend works to reduce traffic impacts.
Every effort will be made to minimise disruptions during this period; however, some impacts are unavoidable. Impacts during the works period will include temporary road closures and bus detours, however all nearby driveways will remain accessible during the works.
Project Background
Recent inspections and community feedback had identified that there are regular unsafe traffic maneuvers been undertaken by members of the public.
The design that incorporates the continuation of the bluestone centre median and current architectural landscape and will lower the risk of the unsafe traffic maneuvers.
The works will be completed by Cord Civil.
Site works map