Latest Update
August 2025
Key activities to date:
Works coming up:
Weekend road closures are no longer in place. Lane closures outside of peak hours will continue to September 2025, when the works are expected to be completed.
Project Summary
This infrastructure upgrade is the continuation of the existing median along Constitution Avenue and will include landscaping.
The works are due to commence in July 2025 and be complete by September 2025.
During the project there will be some periods of weekend works to reduce traffic impacts.
Every effort will be made to minimise disruptions during this period; however, some impacts are unavoidable. Impacts during the works period will include temporary road closures and bus detours, however all nearby driveways will remain accessible during the works.
Project Background
Recent inspections and community feedback had identified a traffic hazard in the form of unsafe traffic maneuvers .
The works incorporates the continuation of the bluestone centre median and current architectural landscape and will lower the risk of the unsafe traffic maneuvers.
The works is undertaken by Cord Civil
Site works map