Intersection of Constitution Avenue and Creswell Street - Infrastructure Upgrades

Image
Project Type
Maintenance
Location
Intersection of Constitution Avenue and Creswell Street
Construction Start Date
1 July 2025
Completion Date
September 2025
Temporary Road or Lake Closures
No

Latest Update

October  2025 

Key activities completed for September include:  

  • Completion of Constitution Avenue asphalt resurfacing and commencement of line marking.  

What to expect on site throughout October:  

Remaining line marking will be complete and then demobilisation from site will occur, with all temporary signs and bollards to be removed.  

All NCA works along Constitution Avenue to prevent illegal right hand turns into Cresswell Street will be completed by the end of October.  

There will be no further updates beyond October for this project. The NCA would like to thank nearby residents, and anyone affected by the works for their patience while these works were being delivered.  

Image
Constitution Ave - Oct 2025 1

 

Image
Constitution Ave - Oct 2025 2

 

Project Summary

This infrastructure upgrade is the continuation of the existing median along Constitution Avenue and will include landscaping. 

The works commenced in July 2025 and are expected to be completed in September 2025. 

During the project there will be some periods of weekend works to reduce traffic impacts. 

Every effort will be made to minimise disruptions during this period; however, some impacts are unavoidable. Impacts during the works period will include temporary road closures and bus detours, however all nearby driveways will remain accessible during the works. 

Project Background

Recent inspections and community feedback had identified a traffic hazard in the form of unsafe traffic maneuvers. 

The works incorporates the continuation of the bluestone centre median and current architectural landscape and will lower the risk of the unsafe traffic maneuvers. 

The works is undertaken by Cord Civil

Site works map

 