February 2026
Throughout December and January the project has progressed with new kerbs, kerb ramps, exposed concrete paths and asphalt carpark surfaces being constructed within the Northern carparks.
The front western car park was completed in late December - ahead of schedule.
The front eastern car park is currently underway with expected completion by early February 2026 to avoid any clash with the upcoming Enlighten Festival.
Following this completion the project will continue along Parliament Square East and be complete by late March 2026.
A full closure of Parliament Square East will need to occur for these works.
More detailed information regarding the current and planned road and carpark closures are available here.
November 2025
Throughout November we have updated new kerbs, kerb ramps and installed exposed concrete paths at the Western side of the front car park.
The existing Asphalt surface has also been removed, and preparation works for the new Asphalt surface is underway.
This first stage of work is currently on track be complete by the end of December 2025.
Stage 2 Works are expected from early January 2026 to mid-February 2026.
To see more information regarding the current and planned road and carpark closures - view here